Part 3 - Digging a hole and filling a hole
Me and my trust Shovel, pick and wheel barrow |
So the site is generally cleared of debris but now the
location needs a bit of leveling. The top part that is basically root balls and
old tree roots are cleared first. Usable topsoil which makes up the first 8 to
10 inches is separated. The roots are thrown in a pile and are taken away to
the dump. The top soil itself is relocated where good soil is need at some
other location. We are then finally to the sub soil which is inert soil. Top
soil is made up of decomposed organic material and is what stuff grows in. It
has nutrients and such but it is no good for building with. So with the sub
soil exposed it’s time to dig the foundation hole. I chose to build on rubble
trench which is basically a French drain. I began to dig a trench two feet wide
and three feet deep all the way around. All of the soil removed was wheel barrowed
to a pile where we would use this very sub soil to form our walls and floor.
Digging was tedious and several times I had the realization that I was not
going to complete this project for many years. At these moments I may have shed
a tear or two, it happens. I figure I moved about 12 yards of subsoil that
summer. Imagine a large dump truck. To make matters more interesting the ground
was filled with rocks and lots of gravel that we used for pathways and the
foundation itself.
I give you one trench 2 ft wide, 3 ft deep |
I must say that as the summer was nearing an end that it
sort of looked at this point like very little had been accomplished. Really I
had dug a hole and filled it back in. Not a lot to look at that’s for sure! At
this point I had a large pile of stones amassed just from digging and logic
said that they would be the start of my foundation wall. I had never done any
of this so don’t forget we are on a huge learning curve. I knew how to build
things in a modern fashion but this concept was outside of my knowledge and
skill set so it was time to learn some new skills! Over the course of the summer I hand shoveled about 20 yards of material. That is a whole lot! Think two dump trucks full minimum!
Next is building the stone foundation wall! Part 4
Perforated pipe is laid first just in case water levels are an issue |
Comments
Post a Comment